![]() |
| May 2008
Summer doesn’t just mean kids out of school and travel plans. It also means construction. Roadwork will be visible throughout Cobb County with a special focus this summer on school and bridge projects.
School Zone Improvements Cobb County's goal for its 2008 program is to complete as many school projects as possible during the summer break. There are 12 projects scheduled to begin construction and most of these will start immediately after school ends in May. Only five school projects remain to be delivered out of 26 projects in the six-year 2005 SPLOST program. Project work schedules will be prioritized to get most of the major construction out of the way to minimize impacts on school circulation and access. Go to www.cobbcip.org/progress-report.htm to view project details and a map of school project locations. These projects will not require road detours although minor traffic delays may occur near these construction sites.
Summer Bridge ReconstructionThere are seven bridge reconstruction projects planned to start this year. Six of these projects will require road closures and construction detours. These projects will improve the safety of the bridges and ensure that safety standard requirements are met. To avoid unnecessary delays, it will be important for the traveling public to carefully take note of the detour signage information. Go to www.cobbcip.org/progress-report.htm for more bridge information and to view detour maps. Jail Expansion The expansion of the Cobb County Adult Detention Center continues to move forward within budget and is scheduled for completion in early 2010. All subcontract packages have been awarded and the excavation for the housing tower and administrative building is complete. Pilings for the foundation are being installed and the first of two tower cranes have been delivered to the site and are in place. Installation of the vertical reinforcing for columns and elevator pit walls continues and installation of the final modular block retaining wall will begin in May. The Visitor Center parking lot and storm drain is completed and the building permit was issued to the contractor in April. Delivery of the pre-engineered metal building is scheduled for May. Renovations to the kitchen and laundry area began in April and are expected to be completed in early 2009. When completed, the expansion will add more than 320,000 square feet and 1,152 beds to the facility, bringing its capacity to 3,077 beds. SPLOST Progress Continues As of April, 212 transportation projects are underway or completed: of these projects, 99 are in the right-of-way acquisition phase, 45 projects are completed and 85 projects have initiated construction. This includes the following:
Moving Ahead of Schedule Cobb DOT is aggressively pursuing project completion of as many projects as possible as part of the 2005 SPLOST program. The following projects will be bid for construction in 2008, with some schedules moved up as much as one year:
Progress on Stilesboro RoadThe 2005 SPLOST program has added significant improvements to the existing Stilesboro Road corridor. Three different projects have been accelerated to open the roads to traffic as soon as possible: Phase I: Stilesboro Road Widening from Mars Hill Road to Rosehedge Way Construction Progress Continues Some major SPLOST Projects continuing under construction include:
Construction Contracts Awarded In March and April, the Cobb County Board of Commissioners awarded the following contracts to:
Lipson Drive RibboncuttingCobb County officials cut the ribbon for Lipson Drive, the two-lane road that provides improved access to Cobb Hospital, during a ceremony Friday. The $2 million project, which connects the East-West Connector to Mulkey Road at Austell Road, is expected to relieve traffic congestion in the Austell Road corridor. The road was named for former WellStar CEO Dr. Robert Lipson, who died in 2006. His widow, Livvy Lipson, took part in the ribboncutting ceremony. Projects on the Horizon:
If you have any questions or comments regarding Cobb SPLOST transportation projects, please email Cobb DOT at cobbdot@cobbcounty.org or contact the Cobb DOT Engineering Division at 770-528-1621. Look for the next SPLOST Transportation e-newsletter in late summer with a look at fall SPLOST activities. |